Streets around Market Square close 7am to 7pm on Sunday 22 November for the lights. London Road keeps its lights, and Pipe Lane shuts 25 to 27 November.
The city centre closes to traffic on Sunday 22 November for the Christmas lights switch-on. The district council’s street closures list names Bore Street, Breadmarket Street, Conduit Street, Dam Street, Market Street and Tamworth Street (from Lombard Street to Conduit Street), closed from 7am to 7pm. The list prints the year as 2025, but the entry sits between other November 2026 events (temporary street closures). The same list closes High Street in Chasetown, from Edwards Road to the Queen Street roundabout, and Ivy Close from 4pm to 9.30pm on Thursday 26 November for its own switch-on.
London Road is the roadworks to plan around in Lichfield this week. Its two-way temporary lights between Cricket Lane and the A38 Swinfen Interchange stay in place, and the county’s page, checked on 19 November, still expects the whole job to be complete by early December. The overnight surfacing closures finished on Monday 16 November (London Road scheme page).
Wood End Lane at Fradley Park also has temporary lights at times, until 11 December, for the new access to the Harrier Centre (Harrier Centre access works).
Also this week:
- Blithbury Road, Rugeley, closes on Monday 23 November for pole cabling work, expected to finish the same day. The county made the order on 17 November (notice of 19 November 2026).
- Pipe Lane, Pipe Ridware, closes from Wednesday 25 to Friday 27 November for a new connection (same notice).
- Uttoxeter Road, Blithbury, closes on Thursday 26 November for cabling work, expected to finish the same day (same notice).
- Main Street and William IV Road, Alrewas, have new parking restrictions from Friday 20 November under a county order made on 17 November (same notice).
- National Highways’ closure report has no A5, A38 or A5148 carriageway closures near Lichfield for this week or next, only the two long HS2 slip road closures at Streethay and Hilliard’s Cross.
- Next up: the county proposes closing Horsey Lane, Upper Longdon, on 2 December (notice of 12 November 2026), then Watling Street at Wall on 4 December and Watery Lane, Curborough, on 9 December (notice of 19 November 2026). Each is one day of pole work, and none of those orders has been made yet.
Updated 21 November: the county has now made the orders for Blithbury Road, Pipe Lane and Uttoxeter Road, and Kings Bromley’s closure was due to end on 19 November. Added the city centre closures for the lights switch-on on 22 November and Chasetown’s on 26 November, and the new proposals for Wall and Curborough.
Updated 19 November: Kings Bromley’s closure reaches its expected finish today. The county’s only new traffic notice since 12 November, published on 18 November, covers roads around Burton and Yoxall, outside the district, so Blithbury Road, Pipe Lane, Uttoxeter Road and Horsey Lane are still proposals. National Highways’ report adds nothing new near Lichfield (road closure report).
Updated 18 November: the A5148 night closure and the last London Road night closure have both passed. The county has published no new traffic notice for the district since 12 November, and National Highways’ report for 17 to 23 November adds nothing new near Lichfield (road closure report).
Updated 16 November: the county has now made the orders for Huddlesford Lane (13 November) and Lichfield Road, Kings Bromley (16 to 19 November), and proposes a one-day closure of Horsey Lane, Upper Longdon, on 2 December (notice of 12 November 2026). Its London Road page is unchanged: Monday 16 November is the last booked night. National Highways’ report for 16 to 22 November still has the A5148 night on 17 November and nothing else new near Lichfield.
Updated 12 November: National Highways has added an overnight closure of the A5148 between Wall and Swinfen roundabouts on 17 November (road closure report). Drayton Lane and the A38 layby at Darnford Lane were both due to finish today. The county’s London Road page is unchanged, and it has published no new traffic notice for the district since 5 November, so Huddlesford Lane and Kings Bromley are still only proposals.
Updated 11 November: the county has changed its London Road plan. Its page now says up to four nights from Tuesday 10 November, plus one night on Monday 16 November, instead of up to six nights from 9 November. The notified dates for Flats Lane (11 November) and for High Street, Chasetown, where the 60 bus is diverted (Chaserider service updates), both end today. Neither notice records an actual reopening, so check the signs. The county has still published no new traffic notice for the district since 5 November.
Updated 10 November: the county’s London Road page, checked today, still gives up to six nights from 9 November and does not say how many are done. No new county traffic notice for the district has been published since 5 November, so Huddlesford Lane and Kings Bromley are still only proposals. National Highways’ report for 10 to 15 November adds nothing near Lichfield.
Updated 9 November: the Stonnall water main closures have passed their 8 November finish date. The county has now made the orders for Drayton Lane (9 to 12 November) and Flats Lane (11 November). Its notice of 5 November proposes three more closures in the north of the district later in the month, at Blithbury and Pipe Ridware, and new parking restrictions on Curborough Road, Reynolds Close and Weston Road in Lichfield.
The rest of this page is what is closed today, what is coming in the next fortnight, the A38 at Streethay, and what parking costs at the end of the drive. Every closure below comes from the statutory traffic order, the highway authority’s own closure report or National Rail, not from a map.
What is closed right now
| Road | Why | In force from | Expected to finish |
|---|---|---|---|
| London Road, Lichfield: two-way temporary signals | New signalised junction | 23 March 2026 | Early December 2026 (night closures finished 16 November) |
| Wood End Lane, Fradley (Harrier Centre): temporary signals at times | New industrial access, phase 1 | 19 October 2026 | 11 December 2026 |
| A5127 Birmingham Road, Wall: 40mph limit | Permanent speed limit, replacing 50mph | 27 October 2026 | Permanent |
| A38 northbound entry slip, Streethay | HS2 realignment | 27 March 2026 | April 2027 |
| A38 southbound entry slip, Hilliard's Cross | HS2 works, Streethay to Fradley | 29 June 2026 | 1 May 2027 |
| Public Footpath 3, Shenstone parish, about 1,030 metres north-east of Footherley Lane | Unsafe footbridge | 6 October 2026 (restriction began 15 September) | Order runs six months |
| Public Footpath 11, Curborough and Elmhurst parish, about 151 metres | Housing development construction | 25 April 2025 | Extended to 25 April 2027 |
| Public Footpath 8, Harlaston parish, about 2,426 metres | Excavating and installing pipework | 14 July 2026 | Order runs to 14 January 2027 |
| Speed limit cut: six lanes at Clifton Campville, Haunton, Highfields and Thorpe Constantine | Temporary speed reduction for access | 24 August 2026 | 24 August 2027 |
| Brookhay Lane, Hilliard's Cross: no vehicles over 13 tonnes | Permanent weight limit (structural) | 9 October 2026 | Permanent |
London Road finishes with the night closures. The scheme builds a new signalised junction into the Cricket Lane development, with a 3 metre shared footway and cycleway on the north side. It started on Monday 23 March, and the county’s page, checked on 19 November, still says the works are expected to be complete by early December 2026, with two-way temporary signals for the whole job. The final surfacing runs overnight, 9pm to 6am, for up to four nights from Tuesday 10 November, plus one night on Monday 16 November, the last one booked, so the overnight closures are now over. Amey is delivering it for the county under a section 278 agreement with the developer, Indurent. Questions go to s278LondonRoad@staffordshire.gov.uk (London Road scheme page).
Wood End Lane at Fradley Park is the county’s second scheme. Its highways team is building a new industrial access to the Harrier Centre, between the accesses to Wesco/Anixter and Halso Fuels. The county’s page gives two phases:
- Phase 1: 19 October to 11 December 2026, with temporary traffic signals at times
- Phase 2: 4 to 29 January 2027, when Wood End Lane will be closed for up to five days, with a signed diversion
Access to homes and businesses is kept open throughout, and the scheme is due to be complete on 29 January 2027 (Harrier Centre access works). The county’s Lichfield roadworks index, checked on 19 November, lists both the Harrier Centre job and London Road as in progress, and nothing else scheduled (Staffordshire County Council, roadworks in Lichfield).
Stonnall and Lynn should now be open. The county’s order for Footherley Lane, Mill Lane and Lynn Lane came into operation on 31 August, and the water main work was anticipated to finish on 8 November. The order does not record the actual reopening (order made 25 August 2026).
A footpath on the Streethay side of the city stays shut until 2027. The county has extended its closure of about 151 metres of Public Footpath 11 in Curborough and Elmhurst parish, running north-west from its junction with Footpath 12 and Streethay Footpath 4, because of housing development construction. There is no alternative route. The order began on 25 April 2025 and now runs to 25 April 2027, or until the danger is over, with the Secretary of State’s approval (notice of 23 October 2026).
A Shenstone footpath is shut for six months. The county made an order on 1 October closing Public Footpath 3 in Shenstone parish, from its junction with Footherley Lane for about 1,030 metres north-east, because of the unsafe condition of the footbridge. It took effect on 6 October and extends a restriction that began on 15 September (notice of 8 October 2026).
Brookhay Lane at Hilliard’s Cross now has a permanent ban on vehicles over 13 tonnes, a structural weight limit the county made on 6 October and which began on 9 October. The documents can be seen at Lichfield Library (notice of 8 October 2026).
The Harlaston footpath closure is odd. The order came into operation on 14 July and closes about 2,426 metres of Public Footpath 8 with no alternative route. The notice expected the work to take 40 days, but it was not published until 17 September and the order runs for six months. You cannot tell from the notice whether the path is walkable today, so look for the plan displayed on site (notice of 17 September 2026).
The speed reduction across the north of the district runs to 24 August 2027, on six lanes at Clifton Campville, Haunton, Highfields and Thorpe Constantine (notice of 20 August 2026).
The end dates above are the ones in each traffic order. A utility can finish early, and the orders do not say when a road actually reopened, so the signs on the day are the final word.
What has changed since 19 November
- Orders made: the county made the orders for Blithbury Road (23 November), Pipe Lane at Pipe Ridware (25 to 27 November) and Uttoxeter Road at Blithbury (26 November) on 17 November (notice of 19 November 2026).
- New proposals: Watling Street at Wall on 4 December and Watery Lane at Curborough on 9 December, both for pole replacement (same notice).
- Alrewas parking: new restrictions on Main Street and William IV Road began on 20 November (same notice).
- Switch-on closures: the city centre on Sunday 22 November, 7am to 7pm, and Chasetown High Street on Thursday 26 November, 4pm to 9.30pm (temporary street closures).
- Finished: Lichfield Road at Kings Bromley was expected to finish on 19 November.
What is coming next
| Road | Why | From | Until | Status |
|---|---|---|---|---|
| City centre: Bore Street, Breadmarket Street, Conduit Street, Dam Street, Market Street, part of Tamworth Street | Christmas lights switch-on | 22 November, 7am | 22 November, 7pm | Listed by the district council |
| Blithbury Road, Rugeley | Pole cabling | 23 November | Same day | Order made |
| Pipe Lane, Pipe Ridware | New connection works | 25 November | 27 November | Order made |
| Uttoxeter Road, Blithbury | Cabling works | 26 November | Same day | Order made |
| High Street and Ivy Close, Chasetown | Christmas lights switch-on | 26 November, 4pm | 26 November, 9.30pm | Listed by the district council |
| Horsey Lane, Upper Longdon | Pole replacement | 2 December | Same day | Proposed |
| Watling Street, Wall | Pole replacement | 4 December | Same day | Proposed |
| Watery Lane, Curborough | Pole replacement | 9 December | Same day | Proposed |
“Proposed” means the county has published a notice that it intends, not less than seven days later, to make the order. Those dates can still change.
Kings Bromley and Huddlesford Lane are now settled. The county proposed both in its notice of 29 October and made both orders on 10 November. Huddlesford Lane closed on 13 November for pole replacement, expected to finish the same day. Lichfield Road at Kings Bromley closed from 16 November for a new gas connection, expected to finish by 19 November. The same notice proposes closing Horsey Lane at Upper Longdon on 2 December for pole replacement, again expected to take a day (notice of 12 November 2026).
Drayton Lane and Flats Lane have passed their finish dates. The county made both orders on 3 November. Drayton Lane at Drayton Bassett was closed from 9 November for new connection works, expected to finish by 12 November, and Flats Lane at Whittington Heath closed on 11 November for pole replacement, expected to finish the same day (Staffordshire County Council notice, 5 November 2026).
Three more closures are booked for late November in the north of the district. The county proposed them on 5 November and made the orders on 17 November (notice of 19 November 2026). It will close Blithbury Road, Rugeley on 23 November for pole cabling, Pipe Lane at Pipe Ridware from 25 November for new connection works, expected to finish by 27 November, and Uttoxeter Road at Blithbury on 26 November for cabling. The Blithbury Road and Uttoxeter Road jobs are each expected to finish the same day.
Parking restrictions are proposed on three Lichfield streets. The notice proposes waiting, loading and parking restrictions on Curborough Road, Reynolds Close and Weston Road. The plans can be seen at Lichfield Library or on the county’s Lichfield consultation map, and comments must reach the county by 26 November 2026, quoting reference CDT6626-2505.
Heading to Tamworth later in the month? The county intends to close Church Street and Corporation Street from 7pm to 6am nightly from 23 November, with the work expected to finish by 6am on 27 November. It also intends to close Hedging Lane from 10pm on 22 November to 6am on 23 November for a bridge inspection. Both are proposals, and both are outside the district (Staffordshire County Council notice, 5 November 2026).
Pool Road in Burntwood could get a raised zebra crossing. The same notice proposes a raised zebra crossing across the full width of Pool Road, 100mm high and 8 metres long, under reference D6850T. The documents can be seen at Burntwood Library, and objections had to reach trafficregulationorderobjections@staffordshire.gov.uk by 12 November 2026, and that window has closed (notice of 22 October 2026).
The A5127 at Wall is now 40mph. The county made a permanent order on 8 September cutting the limit from 50mph, commencing on 27 October. The documents can be seen at Lichfield Library in the Guild of St Mary’s Centre, quoting reference D5967P (notice of 10 September 2026).
Trains: check the planner before you travel
National Rail’s engineering works listing, read on 18 November, had nothing naming Lichfield, Tamworth, Rugeley or the Cross-City line. The West Midlands Railway, London Northwestern and CrossCountry sites refused our requests on 12 November, so we could not check the operators’ own notices. Check the journey planner before you travel. Cross-City trains from Lichfield City to Birmingham run on a different line from Trent Valley. Our Trent Valley October closures story has the background on the two October weekend blockades, which have finished, and the Christmas changes, including three days with no Cross-City trains, are on our Christmas trains page.
The A38 and A5 this week
National Highways’ closure report is re-uploaded daily. Its listings for Tuesday 17 to Monday 23 November, read on 18 November, have no new closures near Lichfield. The one night it did list, the A5148 between Wall and Swinfen roundabouts, ran from 9pm on Tuesday 17 November to 6am on Wednesday 18 November.
- A5 between Weeford and Ventura Park: no closures listed.
- A38 around Lichfield: no carriageway closures listed between Streethay and Fradley. The two HS2 slip closures below, northbound at Streethay and southbound at Hilliard’s Cross, are listed every day.
National Highways’ order closing the southbound layby on the A38 about 30 metres south-west of the Darnford Lane overbridge ran, and has now finished, from 21:00 on Tuesday 10 November to 06:00 on Thursday 12 November, for bridge works. The daily closure report never listed it, so the order is the only record (National Highways notice, 28 October 2026).
Check the report again before a late journey, because nights are added between editions (National Highways road closure report).
The A38 at Streethay
- What: realigning the A38 so HS2 can pass beneath it, between Swinfen Interchange and Hilliard’s Cross.
- Who: HS2 Ltd and its contractor BBV JV, not Staffordshire County Council.
- Closed: the A38 northbound entry slip at Streethay since 27 March 2026, and the southbound entry slip at Hilliard’s Cross since 29 June 2026.
- Now expected to reopen: HS2 says April 2027 for the northbound slip. National Highways lists the Hilliard’s Cross closure to 1 May 2027.
- Also in place: 24-hour narrow lanes, lane and layby closures and speed restrictions between the Cappers Lane junction at Streethay and Fradley.
HS2 had planned a temporary reopening of the northbound slip in October 2026, and has dropped it. It says no temporary alignment passed an independent road safety audit, so the work will run straight through to the permanent road. HS2’s page was last updated on 28 August 2026, and it still says April 2027 on 10 November (HS2, A38 work at Streethay; National Highways road closure report).
For anyone joining the A38 northbound from the Streethay side, that is another winter and spring of the signed detour.
Rights of way: two Ridware paths could become bridleways
Staffordshire County Council has made an order that, if confirmed, would upgrade Public Footpath 0.421 in Mavesyn Ridware parish and part of Public Footpath 0.376(a) in Hamstall Ridware parish to bridleways, and add a new bridleway in Hamstall Ridware. The order can be seen at District Council House on Frog Lane. Objections had to reach the county’s Legal Services Unit by 12 November 2026, quoting LSU/MN/LJ663G, and that window has closed (notice of 1 October 2026).
Who to call about what
Lichfield District Council does not run the roads. Staffordshire County Council is the highway authority for every road in the district, and the A38 works are HS2’s and National Highways’. In practice:
- Potholes, street lights, road closures, traffic orders: Staffordshire County Council, which lists its Lichfield schemes and their status.
- Live works, including utility digs: the one.network map, which is the feed the signs come from.
- The A38 at Streethay: HS2, helpdesk 08081 434 434.
- Motorway and trunk road closures: the National Highways closure report, updated daily.
- Car parks, permits, parking fines in council car parks: Lichfield District Council.
What parking costs when you get there
| Type | Charge |
|---|---|
| Short stay, first 30 minutes | Free (take a ticket) |
| Short stay, 1 hour | £1.00 |
| Long stay, up to 4 hours | £1.60 |
| Long stay, up to 6 hours | £2.60 |
| Long stay, all day | £4.30 |
| Every city car park on Sundays and bank holidays | £2.10 all day |
| Burntwood council car parks | Free, 24 hour maximum stay |
What it means for you: an all-day stay in a Lichfield long stay car park costs £4.30, and the free first half hour in the short stay car parks only counts if you take a ticket. The council car parks in Burntwood are free. The council’s own city car parks page still shows an older long stay tariff of £1.50, £2.50 and £4.00; the parking amendment order and the individual car park records, such as Birmingham Road, give the current figures, and charges there apply from 7.30am to 6.30pm. Every car park, and the Sunday rules, are on our parking in Lichfield page.
The station car park at Lichfield Trent Valley is run commercially, and the alternatives are on our trains to London page.
Frequently asked questions
What roads are closed in Lichfield right now?
Lichfield Road at Kings Bromley is closed until 19 November for a gas connection. Both HS2 entry slip roads on the A38 are closed: northbound at Streethay to April 2027 and southbound at Hilliard’s Cross to May 2027. London Road has two-way temporary lights until early December, and Wood End Lane at Fradley Park has temporary lights at times until 11 December.
Is London Road in Lichfield still closed at night?
No. Staffordshire County Council’s overnight surfacing closures between Cricket Lane and the A38 Swinfen Interchange ran for up to four nights from Tuesday 10 November, plus Monday 16 November, the last night booked. The two-way temporary lights stay until the scheme finishes in early December.
Is the A38 or A5 closed at night near Lichfield?
Not on the A5 or A38 carriageway. National Highways’ report for 17 to 23 November lists no closures there around Lichfield, beyond the two HS2 slip road closures on the A38. The overnight closure of the A5148 between Wall and Swinfen ended at 6am on 18 November.
What roads are closing near Lichfield in the next fortnight?
Settled: Lichfield Road, Kings Bromley (until 19 November). Still proposals: Blithbury Road (23 November), Pipe Lane, Pipe Ridware (25 to 27 November), Uttoxeter Road, Blithbury (26 November) and Horsey Lane, Upper Longdon (2 December).
Are there trains at Lichfield Trent Valley this weekend?
National Rail’s engineering works listing, read on 18 November, names no works at Lichfield, Tamworth or Rugeley. We could not read the operators’ own sites. Check the journey planner before you travel. Cross-City trains from Lichfield City are on a different line.
Has the speed limit changed on Birmingham Road, Wall?
Yes. Staffordshire County Council made a permanent order on 8 September reducing the A5127 Birmingham Road at Wall from 50mph to 40mph, commencing on 27 October 2026.
Why are the A38 slip roads at Streethay closed?
HS2 is realigning the A38 between Swinfen Interchange and Hilliard’s Cross so the railway can pass underneath. The northbound entry slip at Streethay has been closed since March 2026 and is expected to reopen in April 2027, after a planned temporary reopening in October 2026 was cancelled. National Highways also lists the southbound entry slip at Hilliard’s Cross as closed, from 29 June 2026 to 1 May 2027.
What is the diversion for the closed A38 slip road?
Follow Cappers Lane, join the A38 by the southbound off slip road to Swinfen Island, then use the roundabout to rejoin the A38 northbound. The route is signed for the duration of the works.
Who do I report a pothole to in Lichfield?
Staffordshire County Council, not Lichfield District Council. The county is the highway authority for every road in the district. The district council runs the car parks and the parks.
Is parking free in Lichfield?
The first 30 minutes is free in the city’s short stay car parks if you take a ticket. The council car parks in Burntwood are free, with a 24-hour maximum stay. On Sundays and bank holidays every city car park charges £2.10 all day.
Sources
- Staffordshire County Council, London Road new access, checked 18 November 2026, for the early December completion, the night closures (up to four nights from 10 November, plus 16 November) and their diversion, the works, contractor and funding.
- Staffordshire County Council, roadworks in Lichfield, checked 10 November 2026, for the scheme index.
- Staffordshire County Council, new industrial access works at the Harrier Centre, checked 10 November 2026, for the Wood End Lane phases and closure.
- National Highways road closure report, listings for 17 to 23 November 2026 (read 18 November), for the A5148 Wall to Swinfen night closure, the absence of A5 and A38 closures near Lichfield and the two A38 HS2 slip closures.
- National Rail, Stafford to Crewe, 8 November and the National Rail engineering works listing, checked 11 November 2026, for the rail changes.
- Staffordshire County Council notice, 22 October 2026 for the Alrewas Hayes order made on 20 October, the Drayton Lane (November) and Flats Lane proposals, and the Pool Road, Burntwood raised zebra crossing.
- Staffordshire County Council notice, 15 October 2026 for the orders made on 13 October (Netherstowe Lane, Stafford Road, Watery Lane, Springhill Road, Bardy Lane) and the Walsall Road, Little Aston proposal.
- Staffordshire County Council notice, 15 October 2026 for the Church Street, Whittington order and the Drayton Lane proposal.
- Staffordshire County Council notice, 8 October 2026 for the orders made on 6 October (Long Lane, No Mans Heath Road, Little Hay Lane, Little Barrow Walk, Abnalls Lane), the Shenstone Public Footpath 3 closure, the Brookhay Lane weight limit and the Alrewas Hayes proposal.
- Staffordshire County Council notice, 1 October 2026 for The Green, Whittington (order made 29 September).
- National Highways notice, 28 October 2026 for the A38 layby closure order at Darnford Lane overbridge (proposed in its notice of 14 October).
- Staffordshire County Council notice, 29 October 2026 for the Drayton Lane order made on 27 October.
- Staffordshire County Council notice, 29 October 2026 for the Uttoxeter Road, Blithbury and Walsall Road, Little Aston orders made on 27 October, and the Huddlesford Lane and Kings Bromley proposals.
- Staffordshire County Council notice, 12 November 2026 for the Huddlesford Lane and Kings Bromley orders made on 10 November and the Horsey Lane, Upper Longdon proposal.
- Staffordshire County Council notice, 5 November 2026 for the Drayton Lane and Flats Lane orders made on 3 November, the Blithbury Road, Pipe Lane and Uttoxeter Road proposals, and the Curborough Road, Reynolds Close and Weston Road parking proposal (CDT6626-2505).
- Staffordshire County Council notice, 5 November 2026 for the Tamworth proposals at Church Street, Corporation Street and Hedging Lane.
- Staffordshire County Council notice, 23 October 2026 for the Curborough and Elmhurst Public Footpath 11 extension.
- Staffordshire County Council notice, 1 October 2026 for the Ridware bridleway modification order.
- Tamworth Herald notice, 17 September 2026 for the Harlaston Public Footpath 8 closure.
- Staffordshire County Council notice, 10 September 2026 for the A5127 Wall 40mph order.
- Staffordshire County Council notice, 27 August 2026 for the Footherley Lane, Mill Lane and Lynn Lane order.
- Staffordshire County Council notice, 20 August 2026 for the year-long speed reduction in the north of the district.
- HS2, A38 work at Streethay, checked 10 November 2026, for the northbound closure, the cancelled October reopening, the April 2027 date and the diversion.
- National Rail Enquiries engineering works for 17 and 18 October.
- Lichfield District Council parking amendment order and Birmingham Road car park record for tariffs.
Roadworks move and temporary orders take effect only when the signs are out. Check the live map on the day. Checked 18 November 2026.
Have your say